Redbridge College; Week 2

As we complete the second week of refurbishment at Redbridge College, our main man on the ground, David Baguley gives us an update and a low-down on the progress so far.

Redbridge College’s aspirations are to offer the very best facilities for their science courses. Innova have been appointed to convert two former offices into a large science lab, creating more space for practical science classes at the college.

Here’s how the project has developed so far in week two:

First Fix Completion

CONTACT US

0161 477 5300

FOLLOW & SHARE

All drainage, water supply pipe work, electrical cabling and gas pipe work were installed into separate trenches outlined in last week’s article, ensuring that they ran to the correct source and ended at the student benching. Once completed, the trenches were then filled in with concrete, levelled and left to dry ahead of the flooring installation.

blog 1

Flooring Installation

One coat of latex screed was applied after the concrete had dried to level out any imperfections that may have occurred and left to dry for 24 hours. Polysafe slip resistant safety flooring (2mm) was then layed. As the seams and plane were then welded flat and a 3mm bead of clear silicone was applied to the perimeter areas.

blog 2

Related stories

Education

Redbridge College, East London; Week 1

Education

Lab of the Future – The Installation Begins

Education

Lab of the Future Installation – Week 2

Do you have a project in mind?

We would love to hear from you. Give us a call, email or make an enquiry. We are here to share our expertise and answer your questions.

Make an Enquiry
0161 4775300
hello@innovadesigngroup.co.uk
0161 477 5300
click to email us

Follow & Share